Warp Capacity demo — a Filament plugin for resource planning. Drag, book, approve and delete anything; the data is reset every hour. warpui.com About Warp Capacity Docs Ask a question Support
Skip to content

Demand and supply

How much work each role has, against the working time of the people in it. Bars above the line mean you are short of people.

Try it on this page (3)
  1. Find the shortages The table “By role” shows work / working time for each role and week. Red cells with ▲ mean more work than people: backend developers run short in a couple of weeks.
  2. Count projects you have not won yet Change “Tentative projects” from Count fully to Weigh by chance: Woodgrove (60% chance) then counts for 60% of its hours, and the hatched part of the bars gets smaller.
  3. Whom to hire, and when The hiring forecast at the bottom lists roles that stay short four weeks in a row, how many people to hire and when to start looking (hiring takes 8 weeks in this demo). Hiring forecast →

The red number on a role counts the weeks or months in which it is short.

All roles

42 people · Oct 26, 2026 – May 2, 2027

  • Booked people
  • Unfilled placeholders
  • Tentative projects
  • Working time

Vertical axis: Full-time equivalents (1 = one person working full time)

Swipe the chart sideways to see every week.

0 10 20 30 40 50 Oct 26 2026 Nov 16 Dec 7 Dec 28 Jan 18 2027 Feb 8 Mar 1 Mar 22 Apr 12 Oct 26, 2026 – Nov 1, 2026 Booked people: 18.8 FTE Unfilled placeholders: 0.00 FTE Tentative projects: 0.00 FTE Working time: 38.4 FTE 19.6 FTE free Nov 2, 2026 – Nov 8, 2026 Booked people: 19.3 FTE Unfilled placeholders: 0.00 FTE Tentative projects: 0.00 FTE Working time: 38.4 FTE 19.2 FTE free Nov 9, 2026 – Nov 15, 2026 Booked people: 25.7 FTE Unfilled placeholders: 0.00 FTE Tentative projects: 0.00 FTE Working time: 38.9 FTE 13.1 FTE free Nov 16, 2026 – Nov 22, 2026 Booked people: 27.0 FTE Unfilled placeholders: 0.00 FTE Tentative projects: 0.00 FTE Working time: 38.8 FTE 11.8 FTE free Nov 23, 2026 – Nov 29, 2026 Booked people: 29.5 FTE Unfilled placeholders: 0.00 FTE Tentative projects: 0.00 FTE Working time: 39.4 FTE 9.95 FTE free Nov 30, 2026 – Dec 6, 2026 Booked people: 30.2 FTE Unfilled placeholders: 1.00 FTE Tentative projects: 0.50 FTE Working time: 39.4 FTE 7.75 FTE free Dec 7, 2026 – Dec 13, 2026 Booked people: 29.6 FTE Unfilled placeholders: 1.00 FTE Tentative projects: 4.50 FTE Working time: 39.3 FTE 4.18 FTE free Dec 14, 2026 – Dec 20, 2026 Booked people: 30.3 FTE Unfilled placeholders: 1.00 FTE Tentative projects: 4.50 FTE Working time: 39.4 FTE 3.60 FTE free Dec 21, 2026 – Dec 27, 2026 Booked people: 31.4 FTE Unfilled placeholders: 1.00 FTE Tentative projects: 5.00 FTE Working time: 40.4 FTE 3.06 FTE free Dec 28, 2026 – Jan 3, 2027 Booked people: 28.3 FTE Unfilled placeholders: 1.00 FTE Tentative projects: 7.50 FTE Working time: 40.4 FTE 3.68 FTE free Jan 4, 2027 – Jan 10, 2027 Booked people: 29.8 FTE Unfilled placeholders: 1.00 FTE Tentative projects: 7.50 FTE Working time: 39.1 FTE 0.78 FTE free Jan 11, 2027 – Jan 17, 2027 Booked people: 29.0 FTE Unfilled placeholders: 1.00 FTE Tentative projects: 8.50 FTE Working time: 38.7 FTE 0.20 FTE free Jan 18, 2027 – Jan 24, 2027 Booked people: 28.9 FTE Unfilled placeholders: 1.00 FTE Tentative projects: 8.00 FTE Working time: 40.8 FTE 2.89 FTE free Jan 25, 2027 – Jan 31, 2027 Booked people: 27.9 FTE Unfilled placeholders: 1.00 FTE Tentative projects: 8.00 FTE Working time: 39.9 FTE 3.01 FTE free Feb 1, 2027 – Feb 7, 2027 Booked people: 27.3 FTE Unfilled placeholders: 1.00 FTE Tentative projects: 8.00 FTE Working time: 40.3 FTE 3.96 FTE free Feb 8, 2027 – Feb 14, 2027 Booked people: 27.2 FTE Unfilled placeholders: 1.00 FTE Tentative projects: 8.00 FTE Working time: 40.4 FTE 4.21 FTE free Feb 15, 2027 – Feb 21, 2027 Booked people: 24.9 FTE Unfilled placeholders: 1.00 FTE Tentative projects: 8.00 FTE Working time: 39.6 FTE 5.61 FTE free Feb 22, 2027 – Feb 28, 2027 Booked people: 22.9 FTE Unfilled placeholders: 0.00 FTE Tentative projects: 8.00 FTE Working time: 40.4 FTE 9.51 FTE free Mar 1, 2027 – Mar 7, 2027 Booked people: 22.9 FTE Unfilled placeholders: 0.00 FTE Tentative projects: 5.00 FTE Working time: 40.4 FTE 12.5 FTE free Mar 8, 2027 – Mar 14, 2027 Booked people: 19.4 FTE Unfilled placeholders: 0.00 FTE Tentative projects: 5.00 FTE Working time: 40.4 FTE 16.0 FTE free Mar 15, 2027 – Mar 21, 2027 Booked people: 17.2 FTE Unfilled placeholders: 0.00 FTE Tentative projects: 5.00 FTE Working time: 40.3 FTE 18.1 FTE free Mar 22, 2027 – Mar 28, 2027 Booked people: 14.3 FTE Unfilled placeholders: 0.00 FTE Tentative projects: 2.00 FTE Working time: 40.4 FTE 24.2 FTE free Mar 29, 2027 – Apr 4, 2027 Booked people: 12.2 FTE Unfilled placeholders: 0.00 FTE Tentative projects: 2.00 FTE Working time: 40.4 FTE 26.3 FTE free Apr 5, 2027 – Apr 11, 2027 Booked people: 11.1 FTE Unfilled placeholders: 0.00 FTE Tentative projects: 0.00 FTE Working time: 40.4 FTE 29.4 FTE free Apr 12, 2027 – Apr 18, 2027 Booked people: 11.1 FTE Unfilled placeholders: 0.00 FTE Tentative projects: 0.00 FTE Working time: 40.4 FTE 29.4 FTE free Apr 19, 2027 – Apr 25, 2027 Booked people: 6.86 FTE Unfilled placeholders: 0.00 FTE Tentative projects: 0.00 FTE Working time: 40.4 FTE 33.6 FTE free Apr 26, 2027 – May 2, 2027 Booked people: 5.12 FTE Unfilled placeholders: 0.00 FTE Tentative projects: 0.00 FTE Working time: 40.4 FTE 35.3 FTE free

By role

Work / working time, in FTE. ▲ means more work than people. Green means less than 70% of the working time is booked.

Role Oct 26 Nov 2 Nov 9 Nov 16 Nov 23 Nov 30 Dec 7 Dec 14 Dec 21 Dec 28 Jan 4 Jan 11 Jan 18 Jan 25 Feb 1 Feb 8 Feb 15 Feb 22 Mar 1 Mar 8 Mar 15 Mar 22 Mar 29 Apr 5 Apr 12 Apr 19 Apr 26
Designer 2.10 / 7.00 3.00 / 8.00 5.10 / 8.00 5.10 / 8.00 5.35 / 8.00 5.35 / 8.00 5.85 / 8.00 6.10 / 8.00 6.20 / 8.00 6.00 / 8.00 6.60 / 8.00 7.10 / 8.00 6.60 / 8.00 6.60 / 8.00 6.60 / 7.90 6.60 / 8.00 6.60 / 8.00 6.60 / 8.00 6.10 / 8.00 5.00 / 8.00 3.50 / 8.00 3.00 / 8.00 3.00 / 8.00 2.50 / 8.00 2.50 / 8.00 1.00 / 8.00 1.00 / 8.00
Frontend developer 3.00 / 8.55 1.50 / 7.55 4.44 / 8.55 4.90 / 8.55 6.15 / 8.55 6.15 / 8.55 6.70 / 8.50 6.50 / 8.55 6.50 / 8.55 7.10 / 8.55 7.10 / 7.15 9.20 / 8.45 9.10 / 8.75 8.67 / 8.42 8.76 / 8.55 8.76 / 8.55 7.96 / 7.65 8.46 / 8.55 7.46 / 8.55 7.16 / 8.55 6.73 / 8.50 5.26 / 8.55 4.26 / 8.55 3.26 / 8.55 3.26 / 8.55 1.66 / 8.55 1.16 / 8.55
Backend developer 6.84 / 11.4 8.46 / 11.4 8.86 / 11.4 9.36 / 11.4 9.56 / 11.4 11.7 / 11.4 13.6 / 11.3 13.8 / 11.4 14.1 / 11.4 13.3 / 11.4 13.9 / 11.4 11.4 / 10.4 12.1 / 11.3 12.0 / 11.1 11.6 / 11.3 11.6 / 11.4 10.6 / 11.4 8.34 / 11.4 7.34 / 11.4 6.74 / 11.4 6.70 / 11.3 4.10 / 11.4 4.10 / 11.4 3.00 / 11.4 3.00 / 11.4 2.46 / 11.4 2.46 / 11.4
Project manager 4.10 / 6.00 3.54 / 6.00 4.84 / 6.00 5.29 / 6.00 5.29 / 6.00 5.29 / 6.00 5.81 / 6.00 5.49 / 6.00 5.49 / 6.00 5.99 / 6.00 5.99 / 6.00 6.07 / 5.40 5.16 / 6.00 5.04 / 6.00 5.09 / 6.00 5.04 / 6.00 5.04 / 6.00 4.04 / 6.00 3.54 / 6.00 3.54 / 6.00 3.30 / 6.00 2.40 / 6.00 1.70 / 6.00 1.20 / 6.00 1.20 / 6.00 1.20 / 6.00 0.20 / 6.00
QA engineer 2.40 / 3.55 2.40 / 3.55 1.50 / 2.95 1.90 / 3.55 2.15 / 3.55 2.15 / 3.55 2.13 / 3.50 2.90 / 3.55 2.90 / 3.55 2.90 / 3.55 3.30 / 3.55 3.30 / 3.55 3.50 / 3.75 3.17 / 3.42 3.30 / 3.55 3.30 / 3.55 2.80 / 3.55 2.60 / 3.55 2.60 / 3.55 1.60 / 3.55 1.55 / 3.50 1.10 / 3.55 0.70 / 3.55 0.70 / 3.55 0.70 / 3.55 0.54 / 3.55 0.30 / 3.55
Data analyst 0.40 / 2.00 0.40 / 2.00 1.00 / 2.00 0.50 / 1.40 1.00 / 2.00 1.10 / 2.00 1.00 / 2.00 1.10 / 2.00 2.20 / 3.00 1.50 / 3.00 1.40 / 3.00 1.50 / 3.00 1.40 / 3.00 1.40 / 3.00 0.90 / 3.00 0.90 / 3.00 0.90 / 3.00 0.90 / 3.00 0.90 / 3.00 0.40 / 3.00 0.40 / 3.00 0.40 / 3.00 0.40 / 3.00 0.40 / 3.00 0.40 / 3.00 0.00 / 3.00 0.00 / 3.00
All roles 18.8 / 38.4 19.3 / 38.4 25.7 / 38.9 27.0 / 38.8 29.5 / 39.4 31.7 / 39.4 35.1 / 39.3 35.8 / 39.4 37.4 / 40.4 36.8 / 40.4 38.3 / 39.1 38.5 / 38.7 37.9 / 40.8 36.9 / 39.9 36.3 / 40.3 36.2 / 40.4 33.9 / 39.6 30.9 / 40.4 27.9 / 40.4 24.4 / 40.4 22.2 / 40.3 16.3 / 40.4 14.2 / 40.4 11.1 / 40.4 11.1 / 40.4 6.86 / 40.4 5.12 / 40.4

Hiring forecast

Roles that run short in this period. Hire only for what is missing every week of 4 weeks in a row (Short 4 weeks running); a shorter peak shows — and is better covered with overtime or freelancers. Hire rounds it up to whole people. Hiring takes about 8 weeks. Counted in full-time people, week by week.

Role Short from Most short Short 4 weeks running Hire Start hiring by Unfilled placeholders
Backend developer 12 people Nov 30, 2026 2.8 FTE 1.9 FTE 2 people Now (already late) Backend developer ×2, Senior backend developer
Frontend developer 9 people Jan 11, 2027 0.8 FTE 0.2 FTE 1 person Now (already late) Frontend developer ×3
Project manager 6 people Jan 11, 2027 0.7 FTE — Cover with overtime or freelancers — Project manager ×3